All Roads Has Completed All Five Consecutive Phases of Hwy 1 Paving Projects for the BC Ministry of Transportation and Transit



A total of 264,858 metric tonnes of asphalt has been laid down to pave over 356.7 lane kilometers at the five busiest stretches of Hwy 1 in BC.


Each highway paving contract issued by the BC Government comes with rigorous requirements and strict specifications. Through the application of modern paving technologies and advanced automation, All Roads consistently delivers results that not only meet these requirements but exceed them.

Since 2020, All Roads has been selected as the contractor for all five consecutive phases of the Highway 1 paving projects, underscoring our proven efficiency, innovation, and ability to meet the Ministry of Transportation and Infrastructure's highest standards.


Did you know?


Every project tendered by the BC Ministry of Transportation and Transit comes with a strict set of "End Product Specifications" - basically the gold standard for paving in the province. These specs ensure that every inch of road laid in BC is consistently smooth, durable, and top-quality. Fall short of the mark, and you're looking at some steep penalties (and probably a few stern emails). But meet or exceed those standards? You earn the coveted End Product Specification Bonus - a contractor's badge of honor!

Below, you'll see how we've tackled all five phases since 2020. Spoiler alert: we nailed it. Bonus after bonus, phase after phase. What does that say about the quality of our work? We'll let the results - and the Ministry's bonus cheques - speak for themselves.

July 20, 2025

Phase 5

July - October 2025


From Cassiar Tunnel to Willingdon Avenue, Burnaby

  • 33,380 metric tonnes asphalt paved
  • 51.5 lane kilometers
  • End Product Specification Bonus: In-Progress

WATCH VIDEO   READ MORE

Phase 4

July - October 2023


From Brunette River Bridge to Port Mann Bridge, Coquitlam / Burnaby

  • 50,498 metric tonnes asphalt paved
  • 62.4 lane kilometers
  • End Product Specification Bonus: $300,000

WATCH VIDEO   READ MORE

September 23, 2023


October 15, 2022

Phase 3

July 2022 - May 2023


From Port Mann Bridge to Golden Ears Way, Surrey / Coquitlam

  • 84,520 metric tonnes asphalt paved
  • 110.4 lane kilometers
  • End Product Specification Bonus: $570,000
  • Here, we were the first in Canada to use TopCon's PaveLink system on major highway paving project!

WATCH VIDEO   READ MORE

Phase 2

June - October 2021


From Golden Ears Way to 216th Street Interchange, Surrey / Langley

  • 43,460 metric tonnes asphalt paved
  • 54.4 lane kilometers
  • End Product Specification Bonus: $280,000
  • Here, we were the first in BC to use echelon of 4 pavers and 2 milling machines side-by-side!

WATCH VIDEO   READ MORE

June 24, 2021


November 21, 2020

Phase 1

June - October 2020


From Willingdon Ave. to Gaglardi Way, Burnaby

  • 53,000 metric tonnes asphalt paved
  • 78 lane kilometers
  • End Product Specification Bonus: $380,000

WATCH VIDEO   READ MORE