All Roads is proud to have been awarded the fifth phase of the Highway 1 paving project, covering 51.5 lane-kilometres from the Willingdon Interchange to the Cassiar Tunnels. This milestone marks the successful continuation of our work with the Ministry of Transportation and Transit, following the completion of the previous four phases.
Project #: 251627
Contract Value: $7,449,000.00
Status: In-Progress
Start Date: Summer 2025
Completion Date: Autumn 2025
Project Scope Highlights:
33,380 Metric Tonnes of Asphalt Paving
Over 75,000 m² of Full/Variable Depth Asphalt Milling
Over 200 Utility Adjustments
13 km of Barrier Relocates
8 Crash Attenuating Terminals
Over 2,500 New Pavement Markers
Project Associate(s):
Eagle West Truck & Crane
Kontour Geotechnical
Universal Group
Client Information:
Ministry of Transportation and Infrastructure Vincent Ong - Project Manager T: 236-862-0601
Project Supervisor Information:
Ministry of Transportation and Transit Pinder Shahi