District of Hope - Kawkawa Lake Road Improvements



Date Posted : July 31, 2018

Print| Email a Friend| Back


Finished well before scheduled completion date of October 1, 2018. A summary of specific work items includes the following (approx. quantities):


3,380 MT of Asphalt Paving completed on July 31, 2018


Project #: 181002

Contract Value: $681,254.00

Original Contract Value: $620,602.50
Explanation for Variance: Change orders initiated by the District of Hope.

Status: Completed

Start Date: Summer 2018

Completion Date: Autumn 2018

Project Scope Highlights:

  • 12,500 m2 Cold Milling of Asphalt Pavement up to 200mm Depth
  • 12,700 m2 of Road Base Construct New Granular Base
  • Installation of Storm Drywells and Catch Basins.
  • 125m of Extruded Asphalt Curbing
  • 1470 l.m. of Gravel Shouldering
  • 3,380 MT of Asphalt Paving

Client Information:

  • District of Hope
    Kevin Dicken
    T: 604-869-5671