City of Port Coquitlam – 2018 Active Transportation Program

Print| Email a Friend| Back


Completion Date: December 13, 2018

This project was completed on December 13, 2018, with the final contract value $510,082.74.

  • Clearing and Grubbing
  • 750 m3 of Common Excavation
  • 850m of Asphalt Pathway Construction
  • 100m of Concrete Curb, Gutter and Sidewalk Const.
  • Installation of Storm Sewer and Catch Basins.
  • Pavement Markings
  • Electrical – Street Lighting and Overhead Flasher Ped. Crossing
  • Landscaping

Client: City of Port Coquitlam
Project Engineer Information: Mandeep Deol, P.Eng., McElhanney

Share it